On-Prem to Cloud Migration Process
A comprehensive guide to migrating your on-premises infrastructure to AWS cloud, with detailed steps and considerations for minimal downtime.
1. Plan the Migration
- Assessment: Identify current environment (servers, databases, dependencies, configurations)
- Inventory: Document application components and dependencies
- Sizing: Determine AWS resources based on current usage
- Network Design: Plan VPC setup, subnets, security groups, connectivity
- Backup Plan: Create fallback strategy for migration issues
2. Prepare the AWS Environment
- VPC Setup: Create VPC with multi-AZ subnets
- Security: Configure security groups, IAM roles, policies
- Database Configuration: Set up RDS or EC2-based database
- AD Server: Deploy AWS Managed Microsoft AD or EC2-based AD
- Application Server: Launch and configure EC2 instances
3. Migrate Database
- Backup: Create current database backup
- Export/Import: Use AWS DMS or native tools for migration
- Replication: Set up real-time sync with on-prem database
- Validation: Verify data consistency and integrity
4. Migrate Application Server
- Packaging: Package application (Docker, AMIs, binaries)
- Deployment: Deploy on EC2 or Elastic Beanstalk
- DNS Configuration: Update DNS records for AWS environment
5. Migrate Active Directory
- Replication: Create AD replica in AWS using Trust setup
- DNS Sync: Synchronize DNS entries between environments
- Validation: Test authentication and resource access
6. Test and Validate
- End-to-End Testing: Validate complete environment
- Performance Check: Monitor with CloudWatch
- Failover Testing: Simulate failure scenarios
7. Cutover and Go Live
- Schedule Downtime: Coordinate minimal downtime window
- Final Sync: Perform final database sync and traffic switch
- DNS Propagation: Update DNS settings (up to 24 hours)
- Monitoring: Continuous post-migration monitoring
8. Post-Migration Optimization
- Scaling: Implement auto-scaling policies
- Security: Regular security review and improvement
- Cost Optimization: Analyze and optimize with AWS Cost Explorer
Downtime Considerations
- Database Migration: 2-4 hours maintenance window for final sync and cutover
- DNS Propagation: 15 minutes to 24 hours (depending on TTL settings)
- Tip: Use short TTLs during migration to minimize delays